The Supreme Court issued directions on 6 November 2026 to settle the delivery of electricity arrears owed to Himachal Pradesh from the Bhakra-Nangal and Beas projects. Punjab and Haryana must provide 11,973 million units over 20 lean seasons. The direction provides for delivery of electricity itself rather than a single cash payment. It follows a 2011 decree recognising Himachal Pradesh’s entitlement to a share in power from the projects and calling for calculations to establish the amounts due.
The Court addressed both the arrears and Himachal Pradesh’s share of unreimbursed capital costs. It assessed that cost liability at ₹420.77 crore and used an adjustment against the energy entitlement to arrive at the net amount to be delivered. Himachal Pradesh must pay the charges fixed by the Bhakra Beas Management Board for the year in which each portion of electricity is received. The order therefore distinguishes the total volume of electricity owed from the charges payable when it is supplied.
Facts to remember
- Order date: 6 November 2026, in State of Himachal Pradesh v. Union of India.
- Punjab and Haryana are to deliver 11,973 million units of electricity over 20 years.
- Himachal Pradesh’s assessed capital cost liability was ₹420.77 crore.
- The Bhakra Beas Management Board determines the applicable charges for each year of receipt.
Background
Article 131 gives the Supreme Court original jurisdiction over specified disputes between governments where a legal right is at issue, subject to the Constitution. An original suit begins in the Supreme Court itself. In this dispute, the earlier decree settled the entitlement and the later order worked out the quantity and the means of supplying it.
Why it matters for exams
For judiciary and CLAT Polity, use the dispute to revise Article 131 and the difference between declaring a legal entitlement and directing how it must be satisfied.
- Article 131
- Bhakra Beas Management Board
- Himachal Pradesh
- Electricity arrears
- Federalism