Headnote
Electricity Laws : Electricity (Supply) Act, 1948-Section 44(2) and (3)-Dispute regard­ ing escalated project cost of new thermal generating system-Maintainability ~f-When Board approves the reasonable revised project cost at a particular .figure in exercise o,f its prnver under Section 44, under Sec/ion 44(3). Respondent-licensee sought consent from appellant Board for estab· lishment of new thermal generating station. The appellant accorded sanc­ tion. However, the project cost got escalated. The respondent applied for further consent for revised project cost. The
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)