Supreme Court · 2003 INSC 599 · Decided 4 November 2003

United Bank of India v. Ramdas Mahadeo Prashad and ORS.

Court
Supreme Court of India
Citation
2003 INSC 599 · [2003] SUPP. 5 S.C.R. 129
Case number
CIVIL APPEAL No. 8132/2001
Decided
4 November 2003
Bench
S.N. VARIAVA, H.K. SEMA (2-judge bench)
Outcome
Appeal(s) allowed
Case type
Civil
Acts & sections cited
Contract Act Section 62

Headnote

B Contract Act, 1872--Section 62-Enforcement of contract-Dispute between parties-Suit-During pendency parties arriving at Memorandum of Understanding and entering into compromise-However, parties not complying C with the terms and conditions stipulated in the Memorandum of Understanding and acting of Understanding does not amount to concluded contract or novation of contract under Section 62. Respondent filed suit regarding under-writing commitment in public D issue against appellant-bank. During pendency of the suit, parties arrived at Memorandum of Understanding (MOU) in which a

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)