Supreme Court · 2005 INSC 147 · Decided 16 March 2005

Union of India v. Tecco Trichy Engineers & Contractors

Court
Supreme Court of India
Citation
2005 INSC 147 · [2005] 2 S.C.R. 983
Case number
CIVIL APPEAL No. 1784/2005
Decided
16 March 2005
Bench
R.C. LAHOTI, G.P. MATHUR, P.P. NAOLEKAR (3-judge bench)
Outcome
Appeal(s) allowed
Case type
Civil
Acts & sections cited
Arbitration Act Section 2(h), 31(5), 34(1), 34, 31

Headnote

B Arbitration and Conciliation Act, 1996 : ss. 2(h), 31(5), 34(1) read with s.34(3) proviso-Limitation for filing application for setting aside the award-Delivery of copy of award to "party"- C "Party" making application for setting aside award-Arbitration proceedings between award delivered by arbitral tribunal to Chief Engineer concerned-Chief Engineer filing application for setting aside the award alongwith an application for condonation of delay-Application D · contested as being beyond the period of limitation from the date of receipt of copy of award in

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)