Supreme Court · 2006 INSC 705 · Decided 17 October 2006
Union of India v. M/S. Shring Construction Company Private Limited
- Court
- Supreme Court of India
- Citation
- 2006 INSC 705 · [2006] SUPP. 7 S.C.R. 273
- Case number
- CIVIL APPEAL No. 4516/2006
- Decided
- 17 October 2006
- Bench
- G.P. MATHUR, A.K. MATHUR (2-judge bench)
- Outcome
- Appeal(s) allowed
- Case type
- Civil
- Acts & sections cited
- Arbitration Act Section 34, 34(3); Limitation Act Section 14, 5
Headnote
Limitation Act; Section 14/Arbitration and Conciliation Act, 1996; Section 34: A B A private company entering into a contract with Union of India for C construction of residential accommodation-Completion of work-Settling of accounts-Raising of dispute by the Company-Appointment of an could be challenged by filing objection in the District Court-Filing of objections with application for condonation of delay- D Dismissed by District Court-First Appeal dismissed by High Court-On appeal, Held: The question regarding condonation of delay seems not to have been examined by the
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)