Supreme Court · 2013 INSC 637 · Decided 18 September 2013
U.P. Power Corporation LTD. v. N.T.P.C. LTD. & ORS.
- Court
- Supreme Court of India
- Citation
- 2013 INSC 637 · [2013] 9 S.C.R. 805
- Case number
- CIVIL APPEAL No. 4117/2006
- Decided
- 18 September 2013
- Bench
- T.S. THAKUR, VIKRAMAJIT SEN (2-judge bench)
- Outcome
- Dismissed
- Case type
- Civil
- Acts & sections cited
- Electricity Act Section 70
Headnote
CENTRAL ELECTRICITY REGULA TORY COMMISSION (TERMS AND CONDITIONS FOR DETERMINATION OF TARIFF) REGULATIONS, 2001: Regulation 2.5 read with Regulation 1.9 - Taking over of Thermal Power Station - Excess expenditure - Fixation of tariff - Relevant period being 1.4.2001 to 31.3.2004 - Held: Basis A B has to be the "actual capital expenditure" D incurred on the completion of the project -- But where the actual expenditure exceeds the approved expenditure, the excess so incurred can be taken into consideration to the extent the same is allowed by Central Electricity Authority or an
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)