Supreme Court · 1987 INSC 341 · Decided 19 November 1987

U.P. Co-Operative Federation LTD. v. Singh Consultants & Engineers (P) LTD.

Court
Supreme Court of India
Citation
1987 INSC 341 · [1988] 1 S.C.R. 1124
Case number
CIVIL APPEAL No. 3054/1987
Decided
19 November 1987
Bench
SABYASACHI MUKHERJI, K. JAGANNATHA SHETTY (2-judge bench)
Outcome
Appeal(s) allowed
Case type
Civil
Acts & sections cited
Arbitration Act Section 41

Headnote

Performance of contract-guaranteed performance in accordance ._ with time schedule prescribed-Failure to perform obligation within time stipulated-Effect of-Bank guarantee-Right to invoke-To injunc- c tion against. /~~~ The appellant, a State Government enterprise, on or about May 17, 1983, limited company, for the supply and installation of a vanaspati manufacturing plant at a place in the district of Nainital. The contract bond contemp- D lated guaranteed performance of the work at various stages in accord­ ance with the time schedule prescribed and provided for completion

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)