Supreme Court · 2020 INSC 45 · Decided 15 January 2020
The Executive Engineer, Nimna Dudhna Project, Selu, District Parbhani, Maharashtra the State of Maharashtra & Others ETC. ETC. v. The State of Maharashtra & Others ETC.
- Court
- Supreme Court of India
- Citation
- 2020 INSC 45 · [2020] 1 S.C.R. 84
- Case number
- CIVIL APPEAL No. 246/2020
- Decided
- 15 January 2020
- Bench
- ASHOK BHUSHAN, M.R. SHAH (2-judge bench)
- Outcome
- Appeal(s) allowed
- Case type
- Civil
- Acts & sections cited
- Land Acquisition Act
Headnote
Land Acquisition - Statutory benefits and interest for the delayed period in approaching the High Court - Respondents/ original claimants claimed parity in compensation with other land owners delay of five and a half years in preferring the appeals by the original claimants before the High Court challenging the judgment and award passed by the Reference Court - The High Court enhanced the amount of compensation at par with the other land owners/claimants and condoned the