Supreme Court · 2021 INSC 711 · Decided 10 November 2021

The Executive Engineer, Gosikhurd Project Ambadi, Bhandara, Maharashtra Vidarbha Irrigation Development Corporation v. Mahesh and Others

Court
Supreme Court of India
Citation
2021 INSC 711 · [2021] 9 S.C.R. 1123
Case number
CIVIL APPEAL No. 6673/2021
Decided
10 November 2021
Bench
A.M. KHANWILKAR, SANJIV KHANNA (2-judge bench)
Outcome
Appeal(s) allowed
Case type
Civil
Acts & sections cited
Constitution; Land Acquisition Act Section 25, 24(1)(a), 30, 11A

Headnote

Right to Fair Compensation and Transparency in Land Acquisition, Rehabilitation and Resettlement Act, 2013: ss. 25 and 24(1)(a) - Interpretation of s. 24(1)(a) - Determination of period within which an award to be 11A of the 1894 Act and s. 25 of the 2013 Act prescribe two different periods of limitation - If two year period for making an award in terms of s.11A of the 1894 Act is applied to awards made u/s. 24(1)(a), it may lead to practical absurdities and anomalies - This would mitigate