Supreme Court · 2007 INSC 447 · Decided 20 April 2007
Tamil Nadu State Electricity Board v. Central Electricity Regulatory Commission and ORS.
- Court
- Supreme Court of India
- Citation
- 2007 INSC 447 · [2007] 5 S.C.R. 416
- Case number
- CIVIL APPEAL No. 2149/2006
- Decided
- 20 April 2007
- Bench
- H.K. SEMA, V.S. SIRPURKAR (2-judge bench)
- Outcome
- Dismissed
- Case type
- Civil
- Acts & sections cited
- Electricity Act
Headnote
. ' Central Electricity Regulatory Commission (Terms and Conditions of >-· Tarriff) Regulations, 2001; Regulation 2. 7(d)(iv)/Electricity Act, 2003; S. I 25: c Operation and Maintenance/expenses including insurance-Revision-· Escalation factor for the deviation between 4.8% and In terms of Regulation 2. 7(d)(iv) escalation factor of 6% is to be used for revising other charges- On each year the escalation factor would be computed on the basis of actual D inflation data-In case, the deviation factor works out to be within 20% of the standard escalation factor of 6% such
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)