Supreme Court · 2009 INSC 580 · Decided 22 April 2009

State of Rajasthan & ANR. v. MIS. Ferro Concrete Construction PVT. LTD.

Court
Supreme Court of India
Citation
2009 INSC 580 · [2009] 10 S.C.R. 31
Case number
CIVIL APPEAL No. 2764/2009
Decided
22 April 2009
Bench
R.V. RAVEENDRAN, LOKESHWAR SINGH PANTA (2-judge bench)
Outcome
Appeal(s) allowed
Case type
Civil
Acts & sections cited
Arbitration Act Section 30

Headnote

ARBITRATION ACT, 1940 s.30- Setting aside of award- Held: When there is no c allegation of moral misconduct against arbitrator, award can be attacked if there was legal misconduct on the part of the ~ arbitrator in making the award and/or if there was an error apparent the award - In the instant case, the D arbitrator, in respect of claims 1 and 37-A of the contractor and rate of interest payable to contractor (claims 12 and 13) committed a legal misconduct by ignoring terms of contract and it was also a case of error apparent on the face of award - In a

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)