Supreme Court · 1979 INSC 36 · Decided 13 February 1979
State of Maharashtra & ANR. v. Digambar Balwant Kulkarni
- Court
- Supreme Court of India
- Citation
- 1979 INSC 36 · [1979] 3 S.C.R. 188
- Case number
- CIVIL APPEAL No. 2010/1969
- Decided
- 13 February 1979
- Bench
- P.N. BHAGWATI, A.D. KOSHAL (2-judge bench)
- Outcome
- Appeal(s) allowed
- Case type
- Civil
Headnote
OF MAHARASHTRA & ANR. V• DIGAMBAR BALWANT KULKARNI February 13, 1979 [P. N. BHAGWATI AND AD. KoSHAL, JJ.J Contract-Stipulated titne as essence of contract-Meaning of -Right to rescind the contract-When accrues. • Clause (2) of a works contract entered into by the plaintiff by the contractor, and that the contractor shall pay compensation at a i D certain percentage for every day when the work re1nained unfinished after the proper dates. One of the three courses open to the defendant under cl. (3) was to rescind the contract in case the contractor rendered
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)