Supreme Court · 1979 INSC 36 · Decided 13 February 1979

State of Maharashtra & ANR. v. Digambar Balwant Kulkarni

Court
Supreme Court of India
Citation
1979 INSC 36 · [1979] 3 S.C.R. 188
Case number
CIVIL APPEAL No. 2010/1969
Decided
13 February 1979
Bench
P.N. BHAGWATI, A.D. KOSHAL (2-judge bench)
Outcome
Appeal(s) allowed
Case type
Civil

Headnote

OF MAHARASHTRA & ANR. V• DIGAMBAR BALWANT KULKARNI February 13, 1979 [P. N. BHAGWATI AND AD. KoSHAL, JJ.J Contract-Stipulated titne as essence of contract-Meaning of -Right to rescind the contract-When accrues. • Clause (2) of a works contract entered into by the plaintiff by the contractor, and that the contractor shall pay compensation at a i D certain percentage for every day when the work re1nained unfinished after the proper dates. One of the three courses open to the defendant under cl. (3) was to rescind the contract in case the contractor rendered

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)