Supreme Court · 2010 INSC 537 · Decided 20 August 2010

Sree Kamatchi Amman Constructions v. The Divisional Railway Manager (Works), Palghat & ORS.

Court
Supreme Court of India
Citation
2010 INSC 537 · [2010] 10 S.C.R. 487
Case number
CIVIL APPEAL No. 6815/2010
Decided
20 August 2010
Bench
R.V. RAVEENDRAN, H.L. GOKHALE (2-judge bench)
Outcome
Dismissed
Case type
Civil
Acts & sections cited
Arbitration Act Section 37(1), 34

Headnote

A B Interest - Award of - Contract - Arbitration - Award refusing interest for pre-reference period and pendente lite - C Propriety of - Held: Award of interest for such period was rightly denied by arbitral tribunal - General conditions of the contract between barred award of interest - In view of s. 37(1) of Arbitration and Conciliation Act, arbitral tribunal is bound by the terms of the contract and thus cannot D award interest for pre-reference period or pendente lite - Arbitration and Conciliation Act, 1996 - s. 37(1) - Contract. First

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)