Supreme Court · 2010 INSC 11 · Decided 5 January 2010
Snehadeep Structures Private Limited v. Maharashtra Small Scale Industries Development Corporation LTD.
- Court
- Supreme Court of India
- Citation
- 2010 INSC 11 · [2010] 1 S.C.R. 76
- Case number
- CIVIL APPEAL No. 10/2010
- Decided
- 5 January 2010
- Bench
- TARUN CHATTERJEE, V.S. SIRPURKAR (2-judge bench)
- Outcome
- Case Partly allowed
- Case type
- Civil
- Acts & sections cited
- CPC; Arbitration Act Section 34, 4
Headnote
Interest on Delayed Payment to Small Scale and C Ancillary Undertakings Act, 1993 - s. 7 - Expression 'appeal' under - Scope of - Held: Word 'appeal' u/s 7 includes an application uls 34 of Arbitration Act in view of language of s. 7, object of legislation of the term 'appeal' - Arbitration and Conciliation Act, 1996 - s.34 - D Interpretation of Statutes. Interpretation of Statutes - In case of doubt about meaning of a word in a statute, the interpretation which harmonizes the object and purpose of the statute should be E adopted. Words and Phrases
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)