Supreme Court · 2025 INSC 697 · Decided 15 May 2025
Power Grid Corporation of India Limited v. Madhya Pradesh Power Transmission Company
- Court
- Supreme Court of India
- Citation
- 2025 INSC 697 · [2025] 5 S.C.R. 2062
- Case number
- CIVIL APPEAL No. 6847/2025
- Decided
- 15 May 2025
- Bench
- J.B. PARDIWALA, R MAHADEVAN (2-judge bench)
- Outcome
- Appeal(s) allowed
- Case type
- Civil
- Acts & sections cited
- Electricity Act Section 79(1), 79, 178
Headnote
(i) Whether the CERC, while exercising its functions u/s.79(1) of the Electricity Act, 2003, is circumscribed by statutory regulations enacted u/s.178 of the Act, 2003; (ii) Whether the CERC exercises regulatory or adjudicatory Act, 2003. In other words, what is the scope of the CERC's power to regulate inter-state transmission of electricity and determine tariff for the same under clauses (c) and (d) of s.79(1); (iii) Whether the grant of compensation by the CERC for the delay vide the orders dated 21.01.2020 and
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)