Supreme Court · 2018 INSC 111 · Decided 7 February 2018

Ongc Mangalore Petrochemicals LTD. v. M/S Ans Constructions LTD. & ANR.

Court
Supreme Court of India
Citation
2018 INSC 111 · [2018] 2 S.C.R. 598
Case number
CIVIL APPEAL No. 1659/2018
Decided
7 February 2018
Bench
R.K. AGRAWAL, AMITAVA ROY (2-judge bench)
Outcome
Appeal(s) allowed
Case type
Civil
Acts & sections cited
Arbitration Act Section 11

Headnote

Arbitration and Conciliation Act, 1996 - s.11 - Exercise of power under - When not justified - Appellant awarded contract to respondent no.1 - On 21.09.2012, respondent no.1 submitted No Dues/No Claim Certificate - On 10.10.2012, bill to respondent no.1 - On 24.10.2012, respondent no.1 withdrew the No Dues Certificate stating that it was furnished under duress and coercion - Vide letter dtd. 12.01.2013 to appellant, respondent no.1 submitted claim of Rs. 96,88,48,642/- as losses incurred during execution of

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)