Supreme Court · 2025 INSC 1066 · Decided 2 September 2025

Oil and Natural Gas Corporation LTD. v. M/S G & T Beckfield Drilling Services PVT. LTD.

Court
Supreme Court of India
Citation
2025 INSC 1066 · [2025] 9 S.C.R. 507
Case number
CIVIL APPEAL No. 11324/2025
Decided
2 September 2025
Bench
PAMIDIGHANTAM SRI NARASIMHA, MANOJ MISRA (2-judge bench)
Outcome
Dismissed
Case type
Civil
Acts & sections cited
Arbitration Act Section 31(7)(b), 37(1), 31(7), 37

Headnote

Whether Clause 18.1 of the agreement proscribed payment of pendente lite interest on the sum awarded. Arbitration and Conciliation Act, 1996 - s.31(7)(b) - Award of interest pendente lite on the sum awarded - Court - Challenge to - Clause 18.1 of the agreement relied upon by the appellant to contend that the agreement between the parties proscribed grant of pendente-lite interest: Held: Arbitral tribunal can be denuded of its power to award pendente lite interest only if the

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)