Headnote
Contract: Tender - Bid for installation of Steam Generator Package C - Rejected - Held: Evaporator being an integral part of Steam Generator, Qualified steam Generator Manufacturer would have to be the manufacturer of evaporator itself and could not have outsourced the manufacture thereof was one which had been manufactured not by D Qualified Steam Manufacturer but by a third party, which was not contemplated in the condition of the tender document - Rejection of Bid upheld. The appellant invited bids for supply and installation E of Steam Generator Package for captive coal
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)