Supreme Court · 2018 INSC 1124 · Decided 30 November 2018

Nhpc Limited v. M/S Patel Engineering Limited

Court
Supreme Court of India
Citation
2018 INSC 1124 · [2018] 14 S.C.R. 1101
Case number
CIVIL APPEAL No. 11700/2018
Decided
30 November 2018
Bench
D.Y. CHANDRACHUD, M.R. SHAH (2-judge bench)
Outcome
Disposed off
Case type
Civil
Acts & sections cited
Arbitration Act Section 9, 34

Headnote

Arbitration and Conciliation Act, 1996: ss. 9 and 34 - Post- award application u/s. 9 - Application allowed and the appellant called upon to release the amount covered by the arbitral award - Challenge to, on the ground that the order of the High Court was passed even though the period u/s. 34 was still to expire - Appellant's case that the application u/s.9, filed within the period of limitation prescribed for challenging the award ought not to have been entertained - Issuance of notice in these proceedings and stay of the operation of the impugned order of

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)