Supreme Court · 2005 INSC 619 · Decided 15 December 2005
M/S. Transmission Corporation of A.P. LTD. v. M/S. Lanco Kondapalli Power PVT. LTD.
- Court
- Supreme Court of India
- Citation
- 2005 INSC 619 · [2005] SUPP. 5 S.C.R. 790
- Case number
- CIVIL APPEAL No. 7522/2005
- Decided
- 15 December 2005
- Bench
- S.B. SINHA, P.P. NAOLEKAR (2-judge bench)
- Outcome
- Dismissed
- Case type
- Civil
- Acts & sections cited
- Constitution; Arbitration Act Section 9; Electricity Act Section 74
Headnote
Arbitration and Conciliation Act; 1996; Sec!fon 9/Andhra Pradesh Electricity Reforms Act, 1998; Ss.28, 37 and 50/Electrlcil)' Act, 2003; Ss. 83, 84, 86, 94, 145, 154 and 174: r c Power purchase agreem~nt between generator/supplier and Transm_lssion Corporation-Rate fixed on the basis of certain show cause notice to the supplier for re.fixing capacity charges-Filing of an application before Civil Court by the D supplier for issuance of permanent injunction against the Corporation- Dismissed by Civil Court-High Court granted an injunction restraining the Corporation from reftxing the