Supreme Court · 2018 INSC 1158 · Decided 5 December 2018

M/S Simplex Infrastructure LTD v. Union of India

Court
Supreme Court of India
Citation
2018 INSC 1158 · [2018] 14 S.C.R. 676
Case number
CIVIL APPEAL No. 11866/2018
Decided
5 December 2018
Bench
D.Y. CHANDRACHUD, VINEET SARAN (2-judge bench)
Outcome
Appeal(s) allowed
Case type
Civil
Acts & sections cited
Arbitration Act Section 34; Limitation Act Section 5, 14

Headnote

Arbitration and Conciliation Act, 1996: s. 34 - Application under - Delay of 514 days in filing - Condonation of delay - If permissible - Held: By virtue of s. 34(3), recourse to the court against an arbitral award cannot prescribed therein i.e. three months - The proviso thereto allows this period to be further extended by another period of thirty days on sufficient cause being shown - The words 'but not thereafter" in the proviso makes the legislative intent clear that statutory period of

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)