Supreme Court · 2002 INSC 301 · Decided 15 July 2002

M/S. Shyama Charan Agarwala and Sons v. Union of India

Court
Supreme Court of India
Citation
2002 INSC 301 · [2002] SUPP. 1 S.C.R. 148
Case number
CIVIL APPEAL No. 4040/2002
Decided
15 July 2002
Bench
D.P. MOHAPATRA, P. VENKATARAMA REDDI (2-judge bench)
Outcome
Disposed off
Case type
Civil
Acts & sections cited
Arbitration Act Section 39

Headnote

ArbitNtitJn Act, 1940-Section 39-Arbitration award-:-Scope of interfere»~ by Court-Parties entering into contract for construction work­ C Disputes referred to arbitrator-Arbitrator accepting the claim and passing t~ t:iWord-Award made rule of the court-High Court partly allowing construction work. Before the work was completed disputes arose D between the parties. The disputes were referred for arbitration. Appellant­ contractors claimed reimbursement of additional cost on account Of the procurement of stone aggregate from crushers of outside sources in lieu of

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)