Supreme Court · 2021 INSC 347 · Decided 22 July 2021
M/S Laureate Buildwell PVT. LTD. v. Charanjeet Singh
- Court
- Supreme Court of India
- Citation
- 2021 INSC 347 · [2021] 6 S.C.R. 673
- Case number
- CIVIL APPEAL No. 7042/2019
- Decided
- 22 July 2021
- Bench
- UDAY UMESH LALIT, HEMANT GUPTA, S. RAVINDRA BHAT (3-judge bench)
- Outcome
- Case Partly allowed
- Case type
- Civil
Headnote
Housing - Builder flat - Rights of subsequent purchaser (re- allottee), when builder does not honour its commitment to deliver the flat within a stipulated time - Refund of amount deposited with developer/ builder in respect of subject flat - Relief of interest on refund - Entitlement to - Held: The nature and extent of relief, to which a subsequent purchaser can be entitled to, would be fact dependent - However, it cannot be said that a subsequent purchaser who steps into the shoes of an original allottee of a housing project in which the
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)