Supreme Court · 2015 INSC 430 · Decided 15 May 2015
M/S. GMG Engineering Industries & ORS. v. M/S Issa Green Power Solution & ORS.
- Court
- Supreme Court of India
- Citation
- 2015 INSC 430 · [2015] 6 S.C.R. 1108
- Case number
- CIVIL APPEAL No. 4472/2015
- Decided
- 15 May 2015
- Bench
- T.S. THAKUR, R. BANUMATHI (2-judge bench)
- Outcome
- Appeal(s) allowed
- Case type
- Civil
- Acts & sections cited
- CPC
Headnote
1108 A MIS. GMG ENGINEERING INDUSTRIES & ORS. v. MIS ISSA GREEN POWER SOLUTION & ORS. B (Civil Appeal No. 4472 of 2015) MAY 15, 2015 [T. S. THAKUR AND R. BANUMATHI, JJ.) Delay - Condonation of - Applications filed u/Or. 9 r c 13 to set aside the ex-parte decrees alongwith the - On appeal, held: Trial court D should not have imposed unreasonable and onerous condition of depositing the entire suit claim in the suits when the issues are yet to be decided on merits - In revision, High Court should have kept in view that the parties were yet to go for trial and
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)