Supreme Court · 2017 INSC 1026 · Decided 10 October 2017

M/S. Duro Felguera, S. A. v. M/S. Gangavaram Port Limited

Court
Supreme Court of India
Citation
2017 INSC 1026 · [2017] 10 S.C.R. 285
Case number
ARBITRATION PETITION No. 30/2016
Decided
10 October 2017
Bench
KURIAN JOSEPH, R. BANUMATHI (2-judge bench)
Outcome
Disposed off
Case type
Arbitration
Acts & sections cited
Constitution

Headnote

A B c Arbitration and Conciliation (Amendment) Act, 2015: ss. 11 (6) and 11 (6A) - GPL awarded tender work to applicant-Foreign company and FGJ-its lndian subsidiary - Later original contract split into five different and separate packages with different job description - One contract with with FGl - Each contract had separate arbitration clause - Dispute between parties - Arbitration clause invoked - FGJ issued four arbitration notices, applicant issued one arbitration notice whereas GPL issued comprehensive arbitration notice consisting single arbitral tribunal D oi1 basis of

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)