Supreme Court · 2019 INSC 958 · Decided 27 August 2019
Jayesh H. Pandya & ANR. v. Subhtex India LTD. & ORS.
- Court
- Supreme Court of India
- Citation
- 2019 INSC 958 · [2019] 11 S.C.R. 765
- Case number
- CIVIL APPEAL No. 6300/2009
- Decided
- 27 August 2019
- Bench
- N.V. RAMANA, MOHAN M. SHANTANAGOUDAR, AJAY RASTOGI (3-judge bench)
- Outcome
- Appeal(s) allowed
- Case type
- Civil
- Acts & sections cited
- Arbitration Act Section 14, 15
Headnote
Arbitration and Conciliation Act 1996: ss. 14 and 15 - Failure or impossibility to act - Arbitration agreement - In terms of the conditions, arbitrator to make award within four months from the date of service of copy of the agreement, however this period could be extended with - Arbitrator unable to complete the arbitral proceedings within four months from the date of the first preliminary meeting in terms of the arbitration agreement and appellants refused to provide consent to extension of time - Issuance of direction by the tribunal to respondent No 1 to
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)