Supreme Court · 2008 INSC 64 · Decided 18 January 2008

J.C. Budhraja v. Chairman, Orissa Mining CORPN. LTD. & ANR.

Court
Supreme Court of India
Citation
2008 INSC 64 · [2008] 1 S.C.R. 821
Case number
CIVIL APPEAL No. 1971/2000
Decided
18 January 2008
Bench
H.K. SEMA, G.P. MATHUR, R.V. RAVEENDRAN (3-judge bench)
Outcome
Case Partly allowed
Case type
Civil
Acts & sections cited
Constitution; Arbitration Act Section 8(2); Limitation Act Section 18

Headnote

~ i Contract - Work contract - On completion, contractor claiming extra payment for the work done beyond the contract - Payment for the work under contract received under protest c - Constitution of Committee for consideration of extra payment - Statement quantifying the claim, - Committee accepting the same only in part - Contractor issuing notice invoking arbitration - Legal heir of the contractor, making a claim before the arbitrafor, different D from the claim made before the Committee -Arbitrator passing ---1 the award for an amount over and above the claimed

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)