Supreme Court · 2011 INSC 99 · Decided 3 February 2011
Indian Oil Corporation LTD. v. M/S. SPS Engineering LTD.
- Court
- Supreme Court of India
- Citation
- 2011 INSC 99 · [2011] 2 S.C.R. 512
- Case number
- CIVIL APPEAL No. 1282/2011
- Decided
- 3 February 2011
- Bench
- R.V. RAVEENDRAN, A.K. PATNAIK (2-judge bench)
- Outcome
- Appeal(s) allowed
- Case type
- Civil
- Acts & sections cited
- Arbitration Act Section 11
Headnote
Arbitration and Conciliation Act, 1996 - s. 11 - Appointment of arbitrator under - Termination of contract C alleging non-completion of work within the stipulated period - Contractor raising claims against the Company and invoking arbitration agreement - Appointment of arbitrator - Counter-claim for the extra cost in getting the work completed through the alternative agency - o Passing of award - However, rejection of the counter claim - Petition uls. 11 for appointment of an arbitrator to decide the said counter claim - Dismissed by the Designate of the Chief Justice of the High Court
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)