Supreme Court · 2004 INSC 175 · Decided 16 March 2004
Hardesh Ores PVT. LTD. v. Timblo Minerals PVT. LTD.,AND ORS.
- Court
- Supreme Court of India
- Citation
- 2004 INSC 175 · [2004] 2 S.C.R. 1212
- Case number
- CIVIL APPEAL No. 8586/2003
- Decided
- 16 March 2004
- Bench
- SHIVARAJ V. PATIL, D.M. DHARMADHIKARI (2-judge bench)
- Outcome
- Case Partly allowed
- Case type
- Civil
- Acts & sections cited
- CPC Section 39
Headnote
Code of Civil Procedure, 1908: Order 39, rr. 1and2-Interim injunction-Iron ore mine-Contractor- C Continuing mining activities claiming renewal of contract by conduct-New contractor filing a suit claiming that mining lease owner had refused to renew the contract of old contractor and entered into. of new contractor-Held, the suit is pending for trial on merits-On the basis of three established principles D for grant of temporary injunction e.g., prim a facie case, balance of convenience and irreparable loss, it would not be appropriate to interfere with the order of High Court at the
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)