Supreme Court · 2014 INSC 994 · Decided 20 August 2014

H. Dohil Constructions CO. (P) LTD. v. Nahar Exports LTD. & ANR.

Court
Supreme Court of India
Citation
2014 INSC 994 · [2014] 8 S.C.R. 424
Case number
CIVIL APPEAL No. 7886/2014
Decided
20 August 2014
Bench
F.M. IBRAHIM KALIFULLA, SHIVA KIRTI SINGH (2-judge bench)
Outcome
Appeal(s) allowed
Case type
Civil
Acts & sections cited
CPC Section 144, 149

Headnote

Delay!Laches: Delay in filing appeal - 9 days delay in filing Regular First Appeals and 1727 days delay in refiling the same - High Court condoning the delay and admitting the appeals subject to payment of cost to other side - Held: Law of limitation is D policy and therefore the principle that in the absence of bona fide reasons the applications for condonation of delay should be strictly construed· assumes significance - Courts are required to weigh the scale of' balance of justice in respect of both parties and this principle cannot

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)