Supreme Court · 2021 INSC 194 · Decided 19 March 2021
Government of Maharashtra (Water Resources Department) Represented BY Executive Engineer v. M/S Borse Brothers Engineers & Contractors PVT. LTD.
- Court
- Supreme Court of India
- Citation
- 2021 INSC 194 · [2021] 3 S.C.R. 193
- Case number
- CIVIL APPEAL No. 995/2021
- Decided
- 19 March 2021
- Bench
- R.F. NARIMAN, BHUSHAN RAMKRISHNA GAVAI, HRISHIKESH ROY (3-judge bench)
- Outcome
- Disposed off
- Case type
- Civil
- Acts & sections cited
- Constitution Article 141; Arbitration Act Section 37, 34(3), 5, 43; Limitation Act Section 116, 117, 5, 29(2), 137
Headnote
Arbitration and Conciliation Act, 1996:s. 37 - Commercial Courts Act, 2015 - Appealable orders - Limitation period for filing appeal - Condonation of delay in filing appeal u/s. of speedy disposal is sought to be achieved both under the Arbitration Act and the CC Act, for appeals filed u/s. 37 of the 1996 Act that are governed by Arts, 116 and 117 of the Limitation Act or s. 13(1A) of the CC Act - s. 13(1A) of the CC Act lays down a period of limitation of 60