Supreme Court · 1994 INSC 181 · Decided 29 April 1994
G. Ramachandra Reddy and CO. v. Chief Engineer, Madras Zone, Military Engineering Service
- Court
- Supreme Court of India
- Citation
- 1994 INSC 181 · [1994] 3 S.C.R. 808
- Case number
- CIVIL APPEAL No. 4378/1994
- Decided
- 29 April 1994
- Bench
- K. RAMASWAMY, N. VENKATACHALA (2-judge bench)
- Case type
- Civil
- Acts & sections cited
- Arbitration Act Section 8(a), 20
Headnote
REDDY AND CO. v. CHIEF ENGINEER, MADRAS ZONE, MILITARY ENGINEERING SERVICE APRIL 29, 1994 [K. RAMASWAMY AND N. VENKATACHALA, JJ.J Arbitration Act, 1940: Sections 8(a) and 20. C Power of Court to appoint Arbitrato,-.Contract-Dispute-Notice to appoint Arbitrator in terms of General Conditions of D Contract the appellant issued notice to the respondent to appoint ar­ bitrator in terms of the contract for adjudicating the dispute which had arisen between them. On respondents' failure to do so the appellants filed a suit uuder Section 20 of the Arbitration Act,
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)