Supreme Court · 2019 INSC 347 · Decided 12 March 2019
Estate Officer, Haryana Urban Development Authority & ANR. v. Gopi Chand Atreja
- Court
- Supreme Court of India
- Citation
- 2019 INSC 347 · [2019] 2 S.C.R. 1000
- Case number
- CIVIL APPEAL No. 5051/2009
- Decided
- 12 March 2019
- Bench
- ABHAY MANOHAR SAPRE, DINESH MAHESHWARI (2-judge bench)
- Outcome
- Dismissed
- Case type
- Civil
- Acts & sections cited
- Limitation Act Section 5
Headnote
Limitation Act: s.5 - Condonation of delay - Delay of 1942 days in filing second appeal - Application seeking condonation of delay rejected by the High Court - Held: Delay was inordinate and Appellant-HUDA is a statutory authority created under the Haryana Urban Development Authority Act, 1977 and has well- established legal department to look after the legal cases in various Courts - Appellants were, therefore, fully aware of the adverse orders passed in the first appeal
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)