Supreme Court · 1988 INSC 63 · Decided 7 March 1988

Continental Construction CO. LTD. v. State of Madhya Pradesh

Court
Supreme Court of India
Citation
1988 INSC 63 · [1988] 3 S.C.R. 103
Case number
SPECIAL LEAVE PETITION (CIVIL) No. 13180/1985
Decided
7 March 1988
Bench
SABYASACHI MUKHERJI, S. RANGANATHAN (2-judge bench)
Outcome
Dismissed
Case type
Civil
Acts & sections cited
Constitution Article 136; Contract Act Section 56; Arbitration Act Section 20

Headnote

B Arbitration Act, 1940--Whether a contractor can claim extra cost and compensation towards rise in prices of material and labour on account of delay on the part of other party to contract in discharge of its obligations and allotment of work under the contract and irivoke arbi­ tration clause 20--0f The petitioner in this application under Article 136 of the Con­ stitution entered into a contract with the respondent State for construc­ tion work. The contract could not be completed within the stipulated time because of alleged gross delay on the part of the State in

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)