Supreme Court · 2009 INSC 479 · Decided 9 April 2009

Cesc LTD. v. Gajendra Haldea and ORS.

Court
Supreme Court of India
Citation
2009 INSC 479 · [2009] 5 S.C.R. 832
Case number
CIVIL APPEAL No. 333/2007
Decided
9 April 2009
Bench
ARIJIT PASAYAT, A.K. GANGULY (2-judge bench)
Outcome
Appeal(s) allowed
Case type
Civil
Acts & sections cited
Electricity Act Section 60, 121, 125

Headnote

Electricity Act, 2003: ss. 60 and 121 -Appellate Tribunal for Electricity- Power of - Plea that Tribunal invoked s. 60 to direct all Regulatory Commissions to fix trading margins as if it involved tariff determination - Held: Order passed by Tribunal cannot be D maintained and is set aside. The the order of the Appellate Tribunal for Electricity. It was contended that in view of s. 60 of the Electricity Act, 2003, the Tribunal was not empowered to fix trading margins in respect of E traders, intermediators etc. in exercise of its revisional supervisory powers u/s 121 of the

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)