Supreme Court · 2018 INSC 1108 · Decided 27 November 2018
Cci Projects (P) LTD. v. Vrajendra Jogjivandas Thakkar
- Court
- Supreme Court of India
- Citation
- 2018 INSC 1108 · [2018] 14 S.C.R. 213
- Case number
- CIVIL APPEAL No. 6784/2018
- Decided
- 27 November 2018
- Bench
- UDAY UMESH LALIT, R. SUBHASH REDDY (2-judge bench)
- Outcome
- Disposed off
- Case type
- Civil
- Acts & sections cited
- Consumer Protection Act Section 23
Headnote
Consumer Protection Act, 1986 - s.23 - Two consumers booked one residential flat each in a building project, which appellant was to construct - Separate agreements in the year 2012 were entered into, by both the consumers with appellant - Possession of flats was to be sum of Rs.85,86,911/- had been deposited in respect of each flat, no possession was delivered by the appellant by August 2014 - The two consumers filed separate complaints against the appellant - During the pendency of the matters, the possession of flats was offered by the appellant
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)