Supreme Court · 2021 INSC 9 · Decided 6 January 2021
Bhaven Construction Through Authorised Signatory Premjibhai K. Shah v. Executive Engineer Sardar Sarovar Narmada Nigam LTD.& ANR.
- Court
- Supreme Court of India
- Citation
- 2021 INSC 9 · [2021] 1 S.C.R. 1
- Case number
- CIVIL APPEAL No. 14665/2015
- Decided
- 6 January 2021
- Bench
- N.V. RAMANA, SURYA KANT, HRISHIKESH ROY (3-judge bench)
- Outcome
- Appeal(s) allowed
- Case type
- Civil
- Acts & sections cited
- Constitution Article 226, 227; Arbitration Act Section 16, 5, 7, 8, 11, 16(2)
Headnote
Constitution of India, 1950 - Arts.226 and 227 - Interference with arbitral process - Scope - Dispute arising out of a contract between appellant and respondent no.1 - Contract had an arbitration clause - no.2 as the sole arbitrator - Application of respondent no.1 u/s.16 of the Arbitration Act disputing jurisdiction of the sole arbitrator, rejected - Writ petition filed by respondent no.1 - Allowed by High Court - Whether arbitral process could be interfered
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)