Supreme Court · 2015 INSC 185 · Decided 10 March 2015
Bhargava & Associates PVT. LTD. & ORS. v. Union of India and ORS.
- Court
- Supreme Court of India
- Citation
- 2015 INSC 185 · [2015] 2 S.C.R. 794
- Case number
- CIVIL APPEAL No. 5099/2008
- Decided
- 10 March 2015
- Bench
- VIKRAMAJIT SEN, C. NAGAPPAN (2-judge bench)
- Outcome
- Disposed off
- Case type
- Civil
- Acts & sections cited
- Land Acquisition Act Section 11
Headnote
B c Right to Fair Compensation and Transparency in Land Acquisition Rehabilitation and Resettlement Act, 2013 - s. 24(2) - Deemed lapse of acquisition proceedings under - When can be declared- Held: Factum of award uls. 11 of the 1894 Act must be established and the said award must o have been the commencement of the Act - Once the aforesaid is established, possession is found to not have been taken, or compensation not paid, then the proceedings shall be deemed to have lapsed - In the instant case, land owners submission that either possession E still with them or compensation
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)