Supreme Court · 2024 INSC 631 · Decided 27 August 2024

Bangalore Electricity Supply Company Limited v. Hirehalli Solar Power Project LLP & Others

Court
Supreme Court of India
Citation
2024 INSC 631 · [2024] 8 S.C.R. 1024
Case number
CIVIL APPEAL No. 7595/2021
Decided
27 August 2024
Bench
PAMIDIGHANTAM SRI NARASIMHA, PANKAJ MITHAL (2-judge bench)
Outcome
Dismissed
Case type
Civil
Acts & sections cited
Contract Act Section 32, 56; Electricity Act Section 125, 32

Headnote

Whether the extension of the Scheduled Commissioning Date (SCD) was occasioned under the force majeure clause of the Power Purchase Agreement (PPA), and consequently, whether the reduction in tariff payable to the respondents - State of Karnataka introduced a policy dated 26.08.2014 to identify and promote solar energy projects by land-owning farmers - These solar power plants of 1-3 MW capacity would generate and sell power to the State Electricity (Distribution) Supply Companies at the tariff

Search related judgments