Supreme Court · 2013 INSC 542 · Decided 16 August 2013

Assistant Engineer, Rajasthan State Agriculture Marketing Board, Sub-Division, Kota v. Mohan Lal

Court
Supreme Court of India
Citation
2013 INSC 542 · [2013] 9 S.C.R. 91
Case number
CIVIL APPEAL No. 6795/2013
Decided
16 August 2013
Bench
RAJENDRA MAL LODHA, MADAN B. LOKUR (2-judge bench)
Outcome
Case Partly allowed
Case type
Civil
Acts & sections cited
Limitation Act; Industrial Disputes Act Section 25

Headnote

Labour Law: C Termination of services of workman - Industrial dispute raised belatedly - No objection as to delay raised - Reinstatement ordered by Labour Court holding that termination was in violation of s.25-F o ID Act - Held: Delay D in raising industrial dispute is which the Labour Court must keep in view, notwithstanding whether or not such objection has been raised -- Legal position to be followed in case of non-compliance of s.25-F, emphasized - In the instant case, workman worked as a work- E charged employee for 286 days - Labour Court did not

Search related judgments

Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)