Supreme Court · 2020 INSC 205 · Decided 18 February 2020

Assistant Engineer (D1), Ajmer Vidyut Vitran Nigam Limited & ANR. v. Rahamatullah Khan Alias Rahamjulla

Court
Supreme Court of India
Citation
2020 INSC 205 · [2020] 2 S.C.R. 929
Case number
CIVIL APPEAL No. 1672/2020
Decided
18 February 2020
Bench
UDAY UMESH LALIT, INDU MALHOTRA (2-judge bench)
Outcome
Disposed off
Case type
Civil
Acts & sections cited
Limitation Act Section 17(1)(c); Electricity Act Section 56(2), 56

Headnote

Electricity Act, 2003: s. 56(2) - Disconnection of supply in default of payment - Term 'first due' in s.56(2) - Meaning of - Commencement limitation period of two years, when - Held: Electricity charges would become "first due" only after to the consumer, even though the liability to pay may arise on the consumption of electricity - Period of limitation of two years would commence from the date on which the electricity charges became "first due" u/s. 56(2) - This provision restricts the right of the