Headnote
Arbitration and Conciliation Act, I 996-s. I I (6)-Dispute between ~ ...... c Company and the Contractor-Agreement between them contained an arbitration clause-Issue of appointing arbitrator-On application of Company, High Court directing the matter to be placed before the Chief Justice-Appeal by had ... already nominated its arbitrator-Parties agreed on a consensual D arrangement-Appeal accordingly disposed. of-Company to nominate its , .. arbitrator within 30 days-Thereafter Chief Justice of High Court to nominate the Presiding Arbitrator. ~ ,, Respondent-company had entered
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)