Supreme Court · 2017 INSC 894 · Decided 12 September 2017
Aravali Power Company PVT. LTD. v. MIS. Era Infra Engineering LTD.
- Court
- Supreme Court of India
- Citation
- 2017 INSC 894 · [2017] 11 S.C.R. 497
- Case number
- CIVIL APPEAL No. 12627/2017
- Decided
- 12 September 2017
- Bench
- ADARSH KUMAR GOEL, UDAY UMESH LALIT (2-judge bench)
- Outcome
- Disposed off
- Case type
- Civil
- Acts & sections cited
- Constitution; Arbitration Act Section 12, 12(1)
Headnote
497 ARAVALI POWER COMPANY PVT. LTD. v. MIS. ERA INFRA ENGINEERING LTD. (Civil Appeal Nos. 12627-12628 of2017) SEPTEMBER 12,2017 [ADARSH KUMAR GOEL AND UDAY UM ESH LALIT, JJ.[ Arbitration and Conciliation Act. )996 - ss.11(6), 12 and 13 - Appointment of employee of a parzv as arbitrator - appointed its Chief Executive Ojjicer (CEO) as the sole Arbitrator - Parties appeared bejore Arbitrator - However. later Respondent challenged the constitution ofarbitral tribunal - Objection rejected by Arbitrator - Petition by respondent before High Cimrl uls.11(6) for appointing <Ill
Judgments are the courts' own published copies, provided for study; they are not certified copies. Source: Indian Supreme Court & High Court Judgments, Dattam Labs (CC-BY-4.0)