Section 31 — Cessation of powers given by licence under Section 30
Meghalaya Ropeway Act, 2022 (Act No. 14 of 2022) · Preview
(1) If a Promoter authorised by a licence to construct a ropeway does not, within the time specified in the licence:- (a) succeed in raising the full amount of capital required for the completion of…